Tag Archives: National Nuclear Security Administration

U.S. Tritium Production Timelines

Peter Lobner

In the U.S., tritium for nuclear weapons was one of several products produced by the Atomic Energy Commission (AEC) and its successor, the Department of Energy (DOE), during the Cold War.  The machines for tritium production were water-cooled, graphite-moderated production reactors in Hanford, Washington, and heavy water cooled and moderated production reactors at the Savannah River Plant (SRP, now Savannah River Site, SRS) in South Carolina. Lithium “targets,” containing enriched lithium-6 produced at the Y-12 Plant in Oak Ridge Tennessee, were irradiated in these reactors to produce tritium.  Later, tritium was extracted from the targets, purified and packaged for use in nuclear weapons in separate facilities, initially at Hanford and Los Alamos and later at Savannah River.

Today, tritium for the U.S. nuclear weapons stockpile is produced in light water cooled and moderated commercial pressurized water reactors (PWRs) owned and operated by the Tennessee Valley Authority (TVA).  Tritium is extracted from the targets, purified and packaged for use in nuclear weapons at the Savannah River Site (SRS).

The following three timelines provide details on tritium production activities in the Cold War nuclear weapons complex:

The following timeline provides details on the post-Cold War nuclear weapons complex:

These timelines provide supporting information for my post, “U.S. tritium production for the nuclear weapons stockpile – not like the old days of the Cold War,” which is at the following link: https://lynceans.org/all-posts/u-s-tritium-production-for-the-nuclear-weapons-stockpile-not-like-the-old-days-of-the-cold-war/

U.S. Tritium Production for the Nuclear Weapons Stockpile – Not Like the Old Days of the Cold War

Updated 21 May 2020

Peter Lobner

1.  Introduction

Under the Manhattan Project and through the Cold War, the U.S. developed and operated a dedicated nuclear weapons complex that performed all of the functions needed to transform raw materials into complete nuclear weapons.  After the end of the Cold War (circa 1991), U.S. and Russian nuclear weapons stockpiles were greatly reduced.  In the U.S., the nuclear weapons complex contracted and atrophied, with some functions being discontinued as the associated facilities were retired without replacement, while other functions continued at a reduced level, many in aging facilities.

In its current state, the U.S. nuclear weapons complex is struggling to deliver an adequate supply of tritium to meet the needs specified by the National Nuclear Security Administration (NNSA) for “stockpile stewardship and maintenance,” or in other words, for keeping the nuclear weapons in the current, smaller stockpile safe and operational. Key issues include:

  • There have been no dedicated tritium production reactors operating since 1988.  Natural radioactive decay has been steadily reducing the existing inventory of tritium.
  • Commercial light water reactors (CLWRs) have been put into dual-use service since 2003 to produce tritium for NNSA while generating electric power that is sold commercially.  The current tritium production rate needs to increase significantly to meet needs.
  • There has been a continuing decline in the national inventory of “unobligated” (i.e., free from peaceful use obligations) low-enriched uranium (LEU) and high-enriched uranium (HEU). This unobligated uranium can be used for military purposes, such as fueling the dual-use tritium production reactors.
  • There has been no “unobligated” U.S. uranium enrichment capability since 2013.  The technology for a replacement enrichment facility has not yet been selected.
  • The U.S. domestic uranium production industry has declined to a small fraction of the capacity that existed from the mid-1950s to the mid-1980s.  About 10% of uranium purchases in 2018 were from U.S. suppliers, and 90% came from other countries. NNSA’s new enrichment facility will need a domestic source of natural uranium.  
  • There has been no operational lithium-6 production facility since the late 1980s. 
  • There has been a continuing decline in the national inventory of enriched lithium-6, which is irradiated in “targets” to produce tritium.
  • Only one tritium extraction facility exists.

The U.S. nuclear weapons complex for tritium production is relatively fragile, with several milestone dates within the next decade that must be met in order to reach and sustain the desired tritium production capacity.  There is little redundancy within this part of the nuclear weapons complex.  Hence, tritium production is potentially vulnerable to the loss of a single key facility.

This complex story is organized in this post as follows.  

  • Two key materials – Tritium and Lithium 
  • Cold War tritium production
    • Hanford Project P-10 (later renamed P-10-X) for tritium production (1949 to 1954)
    • Hanford N-Reactor Coproduct Program for tritium production (1963 to 1967)
    • Savannah River Plant tritium production (1954 to 1988)
    • Synopsis of U.S. Cold War tritium production
  • The Interregnum of U.S Tritium Production (1988 to 2003)
    • New Production Reactor (NPR) Program
    • Accelerator Tritium Production (ATP)
    • Tritium recycling
  • The U.S. commercial light water reactor (CLWR) tritium production program (2003 to present)
    • Structure of the CLWR program
    • What is a TPBAR?
    • Operational use of TPBARs in TVA reactors
    • Where will the uranium fuel for the TVA reactors come from?
    • Where will the enriched Lithium-6 come from?
    • Where is the tritium recovered?

I put supporting details in a separate post containing four timelines, which you’ll find at the following link: https://lynceans.org/all-posts/u-s-tritium-production-timelines/

2.  Two key materials – Tritium and Lithium

Tritium, or hydrogen-3, is naturally occurring in extremely small quantities (10-18 percent of naturally occurring hydrogen) or it can be artificially produced at great cost.  The current tritium price is reported to be about $30,000 per gram, making it the most expensive substance by weight in the world today. 

Tritium is a radioactive isotope of hydrogen with a half-life of 12.32 years.  Tritium decays into helium-3 by means of negative beta decay, which also produces an electron (e) and an electron antineutrino, as shown below.


Source: nuclear-power.net

Tritium is an important component of thermonuclear weapons.  The tritium is stored in a small, sealed reservoir in each warhead. 

A tritium reservoir, likely manufactured at the 
DOE Kansas City Plant.  Source: 7 Feb 2013,
https://aikenleader.villagesoup.com/

With its relatively short half-life, the tritium content of the reservoir is depleted at a rate of 5.5% per year and must be replenished periodically.  In 1999, DOE reported in DOE/EIS-0271 that none of the weapons in the U.S. nuclear arsenal would be capable of functioning as designed without tritium.

During the Cold War-era, the Atomic Energy Commission (AEC, and its successor in 1977, the Department of Energy, DOE) produced tritium for nuclear weapons in water-cooled, graphite-moderated production reactors in Hanford, Washington and in heavy water cooled and moderated production reactors at the Savannah River Plant (SRP, now Savannah River Site, SRS) in South Carolina.  These reactors also produced plutonium, polonium and other nuclear materials.  All of these production reactors were dedicated defense reactors except the dual-use Hanford-N reactor, which also could produce electricity for sale to the commercial power grid. 

Tritium is produced by neutron absorption in a lithium-6 atom, which splits to form an atom of tritium (T) and an atom of helium-4.  This process is shown below.

Natural lithium is composed of two stable isotopes; about 7.5% lithium-6 and 92.5% lithium-7. To improve tritium production, lithium-6 and lithium-7 are separated and the enriched lithium-6 is used to make “targets” that will be irradiated in nuclear reactors to produce tritium.  The separated, enriched lithium-7 is a valuable material for other nuclear applications because of its very low neutron cross-section.  Oak Ridge Materials Chemistry Division initiated work in 1949 to find a method to separate the lithium isotopes, with the primary goal of producing high purity lithium-7 for use in Aircraft Nuclear Propulsion (ANP) reactors.

Lithium-6 enrichment process development with a focus on tritium production began in 1950 at the Y-12 Plant in Oak Ridge, Tennessee. Three different enrichment processes would be developed with the goal of producing highly-enriched (30 to 95%) lithium-6:  electric exchange (ELEX), organic exchange (OREX) and column exchange (COLEX).  Pilot process lines (pilot plants) for all three processes were built and operated between 1951 and 1955.

Production-scale lithium-6 enrichment using the ELEX process was conducted at Y-12 from 1953 to 1956.  The more efficient COLEX process operated at Y-12 from 1955 to 1963.  By that time, a stockpile of enriched lithium-6 had been established at Oak Ridge, along with a stockpile of unprocessed natural lithium feed material.

The enriched lithium-6 material produced at Y-12 was shipped to manufacturing facilities at Hanford and Savannah River and incorporated into control rods and target elements that were inserted into a production reactor core and irradiated for a period of time.  

After irradiation, these control rods and target elements were removed from the reactor and processed to recover the tritium that was produced.  The recovered tritium was purified and then mixed with a specified amount of deuterium (hydrogen-2, 2H or D) before being loaded and sealed in reservoirs for nuclear weapons.  

Tritium production at Hanford ended in 1967 and at Savannah River in 1988.  The U.S. had no source of new tritium production for its nuclear weapons program between 1988 and 2003.  During that period, tritium recycling from retired weapons was the primary source of tritium for the weapons remaining in the active stockpile. Finally, in 2003, the nation’s new replacement source of tritium for nuclear weapons started coming on line.  

3.  Cold War Tritium Production

3.1  Hanford Project P-10 (later renamed P-10-X) for tritium production (1949 to 1954)

The industrial process for producing plutonium for WW II nuclear weapons was conceived and built as part of the Manhattan Project.  On 21 December 1942, the U.S. Army issued a contract to E. I. Du Pont de Nemours and Company (DuPont), stipulating that DuPont was in charge of designing, building and operating the future plutonium plant at a site still to be selected.  The Hanford, Washington, site was selected in mid-January 1943.

Starting in 1949, the earliest work involving tritium production by irradiation of lithium targets in nuclear reactors was performed at Hanford under Project P-10 (later renamed P-10-X).  By this time, DuPont had built and was operating four water-cooled, graphite-moderated production reactors at Hanford:  B and D Reactors (1944), F Reactor (1945) and H Reactor (1949).  Project P-10-X involved only the B and H Reactors, which were modified for tritium production. 

Tritium was recovered from the targets in Building 108-B, which housed the first operational tritium extraction process line in the AEC’s nuclear weapons complex.  The thermal extraction process employed started with melting the target material in a vacuum furnace and then collecting and purifying the tritium drawn off in the vacuum line.  This tritium product was sent to Los Alamos for further processing and use.  

Hanford site 100-B area.  B Reactor is the tiered building near the center of the photo. The much smaller 108-B tritium extraction process line building is sitting alone on the right.  Source: atomicarchive.com

Project P-10-X provided the initial U.S. tritium production capability from 1949 to 1954 and supplied the tritium for the first U.S. test of a thermonuclear device, Ivy Mike, in November 1952.  Thereafter, most tritium production and all tritium extractions were accomplished at the Savannah River Plant.  

DOE reported: “During its five years of operation, Project P-10-X extracted more than 11 million Curies (Ci) of tritium representing a delivered amount of product of about 1.2 kg.”  For more details, see the report PNNL-15829, Appendix D:  “Tritium Inventories Associated with Tritium Production,” which is available here: 

https://www.pnnl.gov/main/publications/external/technical_reports/PNNL-15829rev0.pdf

3.2.  Hanford N-Reactor Coproduct Program for tritium production (1963 to 1967)

This was a tritium production technology development program conducted in the mid-1960s.  Its primary aim was not to produce tritium for the U.S. nuclear weapons program, but rather to develop technologies and materials that could be applied in tritium breeding blankets in fusion reactors.  After an extensive review of candidate lithium-bearing target materials, the high melting point ceramic lithium aluminate (LiAlO2) was chosen.

Several fuel-target element designs were tested in-reactor, culminating in October 1965 with the selection of the “Mark II” design for use in the full-reactor demonstration.  Targets were double-clad cylindrical elements with a lithium aluminate core. The first cladding layer was 8001 aluminum; the second (outer) cladding layer was Zircaloy-2.

Hanford N Coproduct Target Element.  Source:  BNWL-2097

During the N Reactor coproduct demonstration, four distinct production tests were run, the first two with small numbers of fuel and target columns being irradiated, and the last two runs with over 1,500 fuel and target columns containing about 17 tons LiAlO2.  The last production test, PT-NR-87, recorded the highest N Reactor power level by operating at 4,800 MWt for 31 hours.

The irradiated target elements were shipped to SRP for tritium extraction using a thermal extraction process defined jointly by Pacific Northwest Laboratory (PNL, now Pacific Northwest National Laboratory, PNNL) and Savannah River Laboratories (SRL).  The existing tritium extraction vacuum furnaces at SRP were used.

This completed the Hanford N Reactor Coproduct Program.

More details are available in PNNL report BNWL-2097, “Tritium Production from Ceramic Targets: A Summary of the Hanford Coproduct Program,” which is available at the following link:  

https://www.osti.gov/servlets/purl/7125831

This program provided important experience related to lithium aluminate ceramic targets for tritium production. 

3.3.  Savannah River Plant tritium production (1954 to 1988)

The Savannah River Plant (SRP) was designed in 1950 primarily for a military mission to produce tritium, and secondarily to produce plutonium and other special nuclear materials, including Pu-238.  DuPont built five dedicated production reactors at the SRP and became operational between 1953 and 1955: the R reactor (prototype) and the later P, L, K and C reactors.  

In 1955, the original maximum power of C Reactor was 378 MWt.  With ongoing reactor and system improvements, C Reactor was operating at 2,575 MWt in 1960, and eventually was rated for a peak power of 2,915 MWt in 1967.  The other SRP production reactors received similar reactor and system improvements.  The increased reactor power levels greatly increased the tritium production capacity at SRP.  You’ll find SRP reactor operating power history charts in Chapter 2 of “The Savannah River Site Dose Reconstruction Project -Phase II,” report at the following link:  

https://www.cdc.gov/nceh/radiation/savannah/Chapter_02.pdf

Enriched lithium-6 product was sent from the Oak Ridge Y-12 Plant to SRP Building 320-M, where it was alloyed with aluminum, cast into billets, extruded to the proper diameter, cut to the required length, canned in aluminum and assembled into control rods or “driver” fuel elements.From 1953 to 1955, tritium was produced only in control rods. Lithium-aluminum alloy target rods (“producer rods”) were installed in the septifoil (7-chambered) aluminum control rods in combination with cadmium neutron poison rods to get the desired reactivity control characteristics.

Cross-section of a septifoil control rod.  Source:
The Savannah River Site at Fifty (1950 – 2000), Chapter 13

Starting in 1955, enriched uranium “driver” fuel cylinders and lithium target “slugs” were assembled in a quatrefoil (4-chambered) configuration, which provided much more target mass in the core for tritium production.

Cross-section of a quatrefoil driver fuel / target element. Source:
The Savannah River Site at Fifty (1950 – 2000), Chapter 13
 

Enriched uranium drivers were extruded in Building 320-M until 1957, after which they were produced in the newly constructed Building 321-M.  Production rate varied with the needs of the reactors, peaking in 1983, when the operations in Building 321-M went to 24 hours a day. Manufacturing ceased in 1989 after the last production reactors, K, L and P, were shut down.

K Reactor was operated briefly, and for the last time, in 1992 when it was connected to a new cooling tower that was built in anticipation of continued reactor operation.  K Reactor was placed in cold-standby in 1993, but with no planned provision for restart as the nation’s last remaining source of new tritium production.  In 1996, K Reactor was permanently shut down.

3.4.  Synopsis of U.S. Cold War tritium production

The Federation of American Scientists (FAS) estimated that the total U.S. tritium production (uncorrected for radioactive decay) through 1984 was about 179 kg (about 396 pounds). 

  • DOE reported a total of 10.6 kg (23.4 pounds) of tritium was produced at Hanford:
    • About 1.2 kg (2.7 pounds) was produced at the B and H Reactors during Project P-10-X.
    • The balance of Hanford production (9.4 kg, 20.7 pounds) is attributed to N Reactor operation during the Coproduct Program.  
  • The majority of U.S. tritium production through 1984 occurred at the Savannah River Plant: about 168.4 kg (371.3 pounds).

You can read the FAS tritium inventory report here: https://fas.org/nuke/norris/nuc_87010103d_65c.pdf

4.  The Interregnum of U.S Tritium Production (1988 – 2003)

DOE had shut down all of its Cold War-era production reactors.  Tritium production at Hanford ended in 1967 and at Savannah River in 1988, leaving the U.S. temporarily with no source of new tritium for its nuclear weapons program.  At the time, nobody thought that “temporary” meant 15 years (a period I call the “Interregnum”).  

DOE’s search for new production capacity focused on four different reactor technologies and one particle accelerator technology.  During the Interregnum, the primary source of tritium was from recycling tritium reservoirs from nuclear weapons that had been retired from the stockpile.  This worked well at first, but tritium decays.

4.1 New Production Reactor (NPR) Program

From 1988 to 1992, DOE conducted the New Production Reactor (NPR) Program to evaluate four candidate technologies for a new generation of production reactors that were optimized for tritium production, but with the option to produce plutonium:

  • Heavy water cooled and moderated reactor (HWR)
  • High-temperature gas-cooled reactor (HTGR)
  • Light water cooled and moderated reactor (LWR)
  • Liquid metal reactor (LMR)

Three candidate NPR sites were considered:

  • Savannah River Site
  • Idaho National Engineering Laboratory (INEL, now INL)
  • Hanford Site

The NPR schedule goal was to have the new reactors start tritium production within 10 years after the start of conceptual design.  Details on this program are available in DOE/NP-0007P, “New Production Reactors – Program Plan,” dated December 1990, which is available here:  https://www.osti.gov/servlets/purl/6320732

The NPR program was cancelled in September 1992 (some say “deferred”) after DOE failed to select a preferred technology and failed to gain Congressional budgetary support for the program, at least in part due to the end of the Cold War. 

DOE continued evaluating other options for tritium production, including commercial light water reactors (CLWRs) and accelerator tritium production (ATP).

4.2  Accelerator Tritium Production (ATP)

A candidate ATP design developed by Los Alamos National Laboratory (LANL) was based on a 1,700 MeV (million electron volt) linear accelerator that produced a 170 MW / 100 mA continuous proton beam.  The ATP total electric power requirement was 486 MWe.  The general arrangement of the ATP is shown in the following diagrams.


General arrangement of the ATP.  Source:  LANL

In this diagram, beam energy is indicated along the linear accelerator, increasing to the right and reaching a maximum of 1,700 MeV just before entering a magnetic switch that diverts the beam to the target/blanket or allows to beam to continue straight ahead to a tuning backstop.

Details of the Target / Blanket System.  Source:  LANL

The Target / Blanket System operates as follows:

  • The continuous proton beam is directed onto a tungsten target surrounded by a lead blanket, generating a huge flux of spallation neutrons.
  • Tubes filled with Helium-3 gas are located adjacent to the tungsten and within the lead blanket. 
  • The spallation neutrons created by the energetic protons are moderated by the lead and cooling water and are absorbed by Helium-3 to create about 40 tritium atoms per incident proton.
  • The tritium is continuously removed from the Helium-3 gas in a nearby Tritium Separation Facility. 

The unique feature of on-line, continuous tritium collection eliminates the time and processing required to extract tritium from the target elements used in production reactors.

ATP ultimately was rejected by DOE in December 1998 in favor of producing tritium in a commercial light water reactor (CLWR).

You’ll find an overview of the 1992 to 1998 ATP program here:  http://accelconf.web.cern.ch/AccelConf/pac97/papers/pdf/9B003.PDF

4.3  Tritium recycling

After the end of the Cold War, both the U.S. and Russia greatly reduced their respective stockpiles of nuclear weapons, as shown in the following chart.

Source:  Wikipedia

The decommissioning of many nuclear weapons created an opportunity for the U.S. to temporarily maintain an adequate supply of tritium by recycling the tritium from the reservoirs no longer needed in warheads being retired from service.  However, by 2020, after 32 years of exponential decay at a rate of 5.5% per year, the 1988 U.S. tritium inventory had decayed to only about 17% of the inventory in 1988, when the DOE stopped producing tritium.  You can check my math using the following exponential decay formula:

y = a (1-b)x

where:

y =    the fractional amount remaining after x periods

a =    initial amount = 1

b =    the decay rate per period (per year) = 0.055

x =     number of periods (years) = 32

Recycling tritium from retired and aged reservoirs and precisely reloading reservoirs for installation in existing nuclear weapons are among the important functions performed today at DOE’s Savannah River Site (SRS).  But, clearly, there is a point in time where simply recycling tritium reservoirs is no longer an adequate strategy for maintaining the current U.S. stockpile of nuclear weapons.  A source of new tritium for military use was required.

5.  The U.S. commercial light water reactor (CLWR) tritium production program (2003 to present)

In December 1998, Secretary of Energy Bill Richardson announced the decision to select commercial light water reactors (CLWRs) as the primary tritium supply technology, using government-owned Tennessee Valley Authority (TVA) reactors for irradiation services.  A key commitment made by DOE was that the reactors would be required to use U.S.-origin low-enriched uranium (LEU) fuel.  In their September 2018 report R45406, the Congressional Research Service noted: “Long-standing U.S. policy has sought to separate domestic nuclear power plants from the U.S. nuclear weapons program – this is not only an element of U.S. nuclear nonproliferation policy but also a result of foreign ‘peaceful-use obligations’ that constrain the use of foreign-origin nuclear materials.”

5.1  Structure of the CLWR program

The current U.S. CLWR tritium production capability was deployed in about 12 years, between 1995 and 2007, as shown in the following high-level program plan.

CLWR tritium production program plan.
Source: adapted from NNSA 2001

Since early 2007, NNSA has been getting its new tritium supply for nuclear stockpile maintenance from tritium-producing burnable absorber rods (TPBARs) that have been irradiated in the slightly-modified core of TVA’s Watts Bar Unit 1 (WBN 1) nuclear power plant, which is a Westinghouse commercial pressurized water reactor (PWR) licensed by the U.S. Nuclear Regulatory Commission (NRC).  

TVA’s Watts Bar nuclear power plant.
Source: Oak Ridge Today, 13 Feb 2019

The NRC’s June 2005 “Backgrounder” entitled, “Tritium Production,” provides a good synopsis of the development and nuclear licensing work that led to the approval of TVA nuclear power plants Watts Bar Unit 1 and Sequoyah Units 1 and 2 for use as irradiation sources for tritium production for NNSA.  You find the NRC Backgrounder here:

https://www.nrc.gov/docs/ML0325/ML032521359.pdf

The CLWR tritium production cycle is shown in the following NNSA diagram.  Not included in this diagram are the following:

  • Supply of U.S.-origin LEU for the fuel elements.
  • Production of fuel elements using this LEU
  • Management of irradiated fuel elements at the TVA reactor sites
The current U.S. tritium production cycle.  
Source:  NNSA and Art Explosion via GAO-11-100

PNNL is the TPBAR design authority (agent) and is responsible for coordinating irradiation testing of TPBAR components in the Advanced Test Reactor (ATR) at the Idaho National Laboratory (INL).  Production TPBAR components are manufactured by several contractors in accordance with specifications from PNNL, with WesDyne International responsible for assembling the complete TPBARs in Columbia, South Carolina.  When needed, new TPBARs are shipped to TVA for installation in a designated reactor during a scheduled refueling outage and then irradiated for 18 months, until the next refueling outage.  After being removed from the reactor, the irradiated TPBARs are allowed to cool at the TVA nuclear power plant for a period of time and then are shipped to the Savannah River Site.  

SRS is the only facility in the nuclear security complex that has the capability to extract, recycle, purify, and reload tritium.  Today, the Savannah River Tritium Enterprise (SRTE) is the collective term for the facilities, people, expertise, and activities at the SRS related to tritium production.  SRTE is responsible for extracting new tritium from irradiated TPBARs at the Tritium Extraction Facility (TEF) that became operational in January 2007. They also are responsible for recycling tritium from reservoirs of existing warheads.  The existing Tritium Loading Facility at SRS packages the tritium in sealed reservoirs for delivery to DoD.  You’ll find the SRTE fact sheet at the following link:

https://www.srs.gov/general/news/factsheets/srs_srte.pdf

Program participants and their respective roles are identified in the following diagram.

The current U.S. tritium production program participants.  
Source:  NNSA 2001

5.2  What is a TPBAR?

The reactor core in a Westinghouse commercial four-loop PWR like Watts Bar Unit 1 approximates a right circular cylinder with an active core measuring about 14 feet (4.3 meters) tall and 11.1 feet (3.4 meters) in diameter.  The reactor core has 193 fuel elements, each of which is comprised of a 17 x 17 square array of 264 small-diameter, fixed fuel rods and 25 small-diameter empty thimbles, 24 of which serve as guide thimbles for control rods and one is an instrumentation thimble. 

Rod cluster control assemblies (RCCAs) are used to control the reactor by moving arrays of small-diameter neutron-absorbing control rods into or out of selected fuel elements in the reactor core.  Watts Bar has 57 RCCAs, each comprised of 24 Ag-In-Cd (silver-indium-cadmium) neutron-absorbing rods that fit into the control rod guide thimbles in selected fuel elements. Each RCCA is controlled by a separate control rod drive mechanism.  The geometries of a Westinghouse 17 x 17 fuel element and the RCCA are shown in the following diagrams.


Cross-sectional view of a single Westinghouse 17 x 17 fuel element showing the lattice positions assigned to fuel rods (red) and the thimbles available for instrumentation and control rods (blue). Source:  Syeilendra Pramuditya

Isometric view of a Westinghouse 17 x 17 fuel element showing the fixed fuel rods (red) and a rod cluster control assembly (yellow) that can be inserted or withdrawn for reactivity control.  Sources:  (L) Framatom ANP report BAW-10237, May 2001; 
(R) Westinghouse via NuclearTourist

To produce tritium in a Westinghouse PWR core, lithium-6 targets, in the form of lithium aluminate (LiAlO2) ceramic pellets, are inserted into the core and irradiated.  This is accomplished with the tritium-producing burnable absorber rods (TPBARs), each of which is a small-diameter rod (a “rodlet”) that externally looks quite similar to a single control rod in an RCCA.  During one typical 18-month refueling cycle (actually, up to 550 equivalent full power days), the tritium production per rod is expected to be in a range from 0.15 to 1.2 grams. The ceramic lithium aluminate target is similar to the targets developed in the mid-1960s and used during the Hanford N-Reactor Coproduct Program for tritium production.

A TPBAR “feed batch” assembly generally resembles the shape of an RCCA, but with 12 or 24 TPBAR rodlets in place of the control rods.  The feed batch assembly is a hanging structure supported by the top nozzle adapter plate of the fuel assembly and the TPBAR rodlets are hanging in the guide thimble tubes of the fuel assembly.  The feed batch assembly does not move after it has been installed in the reactor core. 

Since lithium-6 is a strong neutron absorber, the TPBAR functions in the reactor core in a manner similar to fixed burnable absorber rods, which use boron-10 as their neutron absorber.  The reactivity worth of the TPBARs is slightly greater than the burnable absorber rods.

In 2001, Framatome ANP issued Report BAW-10237,  “Implementation and Utilization of Tritium Producing Burnable Absorber Rods (TPBARS) in Sequoyah Units 1 and 2.”   This report provides a good description of the modified core and TPBARs as they would be applied for tritium production at the Sequoyah nuclear plant. Watts Bar should be similar.  The report is here: 

http://citeseerx.ist.psu.edu/viewdoc/download?doi=10.1.1.388.7747&rep=rep1&type=pdf

The feed batch assembly and TPBAR rodlet configurations are shown in the following diagram.

TPBAR feed batch assembly (left); details of an 
individual TPBAR and target pellet (right).  Source:  NNSA 2001

TPBARs were designed for a low rate of tritium permeation from the target pellets, through the cladding and into the primary coolant water.  Tritium permeation performance was expected to be less than 1.0 Curie/one TPBAR rod/year.  With an assumed  maximum of 2,304 TPBARs in the reactor core, the NRC initially licensed Watts Bar Unit 1 for a maximum annual tritium permeation of 2,304 Curies / year.

5.3. Operational use of TPBARs in TVA reactors

NRC issued WBN 1 License Amendment 40 in September 2002,  approving the irradiation of up to 2,304 TPBARs per operating cycle.

For the first irradiation cycle (Cycle 6) starting in the autumn of 2003, TVA received NRC approval to operate with only 240 TPBARs because of issues related to Reactor Coolant System (RCS) boron concentration.  Actual TPBAR performance during Cycle 6 demonstrated a significantly higher rate of tritium permeation than expected; reported to be about 4.0 Curies/one TPBAR/cycle.

TVA’s short-term response was to limit the number of TPBARs per core load to 240 in Cycles 7 and 8 to ensure compliance with its NRC license limits on tritium release. In their 30 January 2015 letter to TVA, NRC stated, “….the primary constraint on the number of TPBARs in the core is the TPBAR tritium release per year of 2,304 Curies per year.”  This guidance gave TVA some flexibility on the actual number of TPBARs that could be irradiated per cycle.  This NRC letter is available here: https://www.nrc.gov/docs/ML1503/ML15030A508.pdf

PNNL’s examinations of TPBARs revealed no design or production flaws.  Nonetheless, PNNL developed design modifications intended to improve tritium permeation performance.  These changes were implemented by the manufacturing contractors, resulting in the Mark 9.2 TPBAR, which was first used in 2008 in WBN 1 Cycle 9. PNNL also is conducting an ongoing irradiation testing programs in the Advanced Test Reactor (ATR) at INL, with the goal of finding a technical solution for the high permeation rate. You’ll find details on this program in a 2013 PNNL presentation at the following link:  https://www.energy.gov/sites/prod/files/2015/08/f26/Senor%20-%20TMIST-3%20Irradiation%20Experiment.pdf

In October 2010, the General Accounting Office (GAO) reported: “no discernable improvement in TPBAR performance was made and tritium is still permeating from the TPBARs at higher-than-expected rates.”  This GAO report is available here:  https://www.gao.gov/products/GAO-11-100

In response to the high tritium permeation rate, the irradiation management strategy was revised based on an assumed permeation rate of 5.0 Curies per TPBAR per year (five times the original expected rate). Even at this higher permeation rate, WBN 1 can meet the NRC requirements in 10 CFR Part 20 and 10 CFR Part 50 Appendix I related to controlling radioactive materials in gaseous and liquid effluents produced during normal conditions, including expected occurrences.

The many NRC license amendments associated with WBN 1 tritium production are summarized below:

  • In License Amendment 40 (Sep 2002), the NRC originally approved WBN 1 to operate with up to 2,304 TPBARs.
  • Cycle 6:  TVA limited the maximum number of TPBARs to be irradiated to 240 based on issues related to Reactor Coolant System (RCS) boron concentration.  Approved by NRC in WBN 1 License Amendment 48 (Oct 2003).
  • Cycles 7 & 8:  WBN 1 continued operating with 240 TPBARs.
  • Cycle 9: First use of TPBARs Mark 9.2 supported TVAs request to increase the maximum number of TPBARs to 400.  Approved by NRC in WBN 1 License Amendment 67 (Jan 2008)
  • Cycle 10: TVA reduced the number of TPBARs irradiated to 240 after discovering that the Mark 9.2 TPBAR design changes deployed in Cycle 9 did not significantly reduce tritium permeation.
  • Cycles 11 to 14: NRC License Amendment 77 9May 2009) allowed a maximum of 704 TPBARs at WBN 1.  TVA chose to irradiate only 544 TPBARs in Cycles 11 and 12, increasing to 704 TPBARs for Cycles 13 & 14.
  • Cycles 15 & beyond:  NRC License Amendment 107 (Aug 2016) allows a maximum of 1,792 TPBARs at WBN 1.

The actual number of TPBARs and the average tritium production per TPBAR during WBN 1 Cycles 6 to 14 are summarized in the 2017 PNNL presentation, “Tritium Production Assurance,” and are reproduced in the following table.

Tritium production, WBN 1 Cycles 6 to 14 (Cycle 14, completed in 2011, is an estimate).  Source: PNNL, Tritium Production Assurance, 11 May 2017

The current tritium production plan continues irradiation in WBN 1 and starts irradiation in Watts Bar Unit 2 (WBN 2) in Cycle 4, which will start after the spring 2022 refueling.  Tritium is assumed to be delivered six months after the end of each cycle.

WBN 1 and WBN 2 TPBAR loading plans. 
Source: “Tritium Production Assurance”, report of the PNNL Tritium Focus Group, Richland, WA, May 11, 2017

See the complete PNNL presentation, “Tritium Production Assurance,” here: https://www.energy.gov/sites/prod/files/2017/06/f34/May%2011%20-%20Stewart%20-%20Tritium%20Production%20Assurance.pdf

As of early 2020, TVA and DOE are not delivering the quantity of tritium expected by NNSA. In July 2019, DOE and NNSA delivered their “Fiscal Year 2020 – Stockpile Stewardship and Management Plan” to Congress.  In this plan, the top-level goal was to “recapitalize existing infrastructure to implement a plan to produce no less than 80 ppy (plutonium pits per year) by 2030.” To meet this goal, NNSA set a target for increasing tritium production to 2,800 grams per two 18-month reactor cycles of production at TVA by 2027. This means two TVA reactors will be producing tritium, and each will have a target of about 1,400 grams per cycle.  This will be quite a challenge for TVA and DOE.

The 2018 Stockpile Stewardship and Management Plan is available here: https://www.energy.gov/sites/prod/files/2018/10/f57/FY2019%20SSMP.pdf

5.4  Where will the uranium fuel for the TVA reactors come from?

The tritium-producing TVA reactors are committed to using unobligated LEU fuel.  That means that the uranium is not encumbered by international obligations that restrict its use for peaceful purposes only. Unobligated uranium has a very special pedigree. The uranium originated from U.S. mines, was processed in U.S. facilities, and was enriched in an unobligated U.S. enrichment facility.  

Today, that front-end of the U.S. nuclear fuel cycle has withered against international competition, as shown in the following chart from the Energy Information Administration (EIA).

Source:  EIA, https://www.eia.gov/energyexplained/nuclear/where-our-uranium-comes-from.php

Since the U.S. has not had an unobligated uranium enrichment facility since 2013, when the Paducah enrichment plant was closed by the Obama administration, there currently is no source of new unobligated LEU for the tritium-producing TVA reactors.

The impending shortage of unobligated enriched uranium eventually could affect tritium production, Navy nuclear reactor operation and other users. This matter has been addressed by the GAO in their 2018 report GAO-18-126, “NNSA Should Clarify Long-Term Uranium Enrichment Mission Needs and Improve Technology Cost Estimates,” which is available here:

https://www.gao.gov/assets/700/690143.pdf

The solution could be a mixture of measures, some of which are discussed briefly below.  

Downblend unobligated HEU to buy time

Currently, the LEU for the TVA reactors is supplied from the U.S. inventory of unobligated LEU, which is supplemented by downblending unobligated HEU.  In September 2018, NNSA awarded Nuclear Fuel Services (NFS) a $505 million contract to downblend 20.2 metric tons of HEU to produce LEU, which can serve as a short-term source of fuel for the tritium-producing TVA reactors.  This contract runs from 2019 to 2025.  Beyond 2025, additional HEU downblending may be needed to sustain tritium production until a longer-term solution is in place.

Build a new unobligated uranium enrichment facility and re-build the associated domestic uranium mining, milling and conversion infrastructure

NNSA is in the process of selecting the preferred technology for a new unobligated enrichment plant.  There are two competing enrichment technologies:  the Centrus AC-100 large advanced gas centrifuge and the Oak Ridge National Laboratory small advanced gas centrifuge, both of which are designed to enrich gaseous uranium hexafluoride (UF6).

NNSA failed to meet its goal of making the selection by the end of 2019.  Regardless of the choice, it will take more than a decade to deploy such a facility.  Perhaps a mid-2030’s date would be a possible target for initial operation of a new DOE uranium enrichment facility.

In the meantime, the atrophied / shutdown US uranium mining, milling and conversion industries need to be rebuilt to once again establish a reliable, domestic source of feed material for DOE’s uranium enrichment operations.  This will be a daunting task given the current sad state of the US uranium production industry.

In May 2020, the US Energy Information Administration (EIA) released its 2019 Domestic Uranium Production Report.  Mining uranium ore or in-situ leaching from underground uranium ore bodies, followed by the production of uranium (U3O8) concentrate (”yellowcake”), are the first steps at the front-end of the nuclear fuel cycle.  The following EIA summary graphic shows the decline of US uranium production, which has been especially dramatic since 2013.

US uranium (U3O8) concentrate production and shipments, 
1996–2019. Source: EIA

A key point reported by the EIA was that total US production of uranium concentrate from all domestic sources in 2019 was only 170,000 pounds (77,111 kg) of U3O8, 89% less than in 2018, from six facilities.  In the graphic, you can see that US annual production in 1996 was about 35 times greater, approximately 6,000,000 pounds (2,721,554 kg).  This EIA report is available at the following link: https://www.eia.gov/uranium/production/annual/

Conversion of U3O8 to UF6 is the next step in the front-end of the nuclear fuel cycle.  Honeywell’s Metropolis Works was built in 1958 to produce UF6 for US government programs, including the nuclear weapons complex.  Therefore, the Metropolis Works should be an unobligated conversion plant and, as such, is an important facility in the nuclear fuel cycle for the US tritium production reactors operated by TVA.  In 2020, the Metropolis Works is the only US facility that can receives uranium ore concentrate and convert it to UF6.

In 1968, Metropolis Works began selling UF6 on the commercial nuclear market. However, since 2017, operations at the Metropolis Works have been curtailed due to weak market conditions for its conversion services and Honeywell has maintained the facility in a “ready-idle” status. In March 2020, the NRC granted the Metropolis Works a 40-year license renewal, permitting operations until March 24, 2060.  When demand resumes, the Metropolis Works should be ready to resume operation.

Recognizing the US national interest in having a viable industrial base for the front-end of the nuclear fuel cycle, President Trump established a Nuclear Fuel Working Group in July 2019.  On 13 April, 2020, the DOE released the “Strategy to Restore American Nuclear Energy Leadership,” which, among other things, includes recommendations to strengthen the US uranium mining and conversion industries and restore the viability of the entire front-end of the nuclear fuel cycle.  You’ll find this DOE announcement and a link to the full report to the President here: https://www.energy.gov/articles/secretary-brouillette-announces-nuclear-fuel-working-groups-strategy-restore-american

Reprocess enriched DOE and naval fuel spent fuel

A large inventory of aluminum clad irradiated fuel exists at SRS, with a smaller quantity at INL.  The only operating chemical separations (reprocessing) facility in the U.S. is the H-Canyon facility at SRS, which can only process aluminum clad fuel.  However, the cost to operate H-Canyon to process the aluminum-clad fuel would be high.

There is a large inventory of irradiated, zirconium-clad naval fuel at INL.  This fuel started life with a uranium enrichment level of 93% or higher.  In 2017, INL completed a study examining the feasibility of processing zirconium-clad spent fuel through a new process called ZIRCEX. This process could enable reprocessing the spent naval fuel stored at INL as well as other types of zirconium-clad fuel.

In 2018, the U.S. Senate approved $15 million in funding for a pilot program at the INL to “recycle” irradiated (used) naval nuclear fuel and produce high-assay, low-enriched uranium (HALEU) fuel with an enrichment between 5% to 20% for use in “advanced reactors.”  It seems that a logical extension would be to also produce LEU fuel to a specification that could be used in the TVA reactors.

In 2018, Idaho Senator Mike Crapo made the following report to the Senate:  “HEU repurposing, from materials like spent naval fuel, can be done using hybrid processes that use advanced dry head-end technologies followed by material recovery, which creates the fuel for our new advanced reactors. Repurposing this spent fuel has the potential of reducing waste that would otherwise be disposed of at taxpayer expense, and approximately 1 metric ton of HEU can create 4 useable tons (of HALEU) for our new reactors.”

Perhaps there is a future for closing the back-end of the naval fuel cycle and recovering some of the investment that went into producing the very highly enriched uranium used in naval reactors.  Because of the high burnup in long-life naval reactors, the resulting HALEU or LEU will have different uranium isotopic proportions than LEU produced in the front-end of the fuel cycle.  This may introduce issues that would have to be reviewed and approved by the NRC before such LEU fuel could be used in the TVA reactors.

Other options

More information on options for obtaining enriched uranium without acquiring a new uranium enrichment facility is provided in Appendix II of GAO-18-126.

5.5  Where will the enriched lithium-6 target material come from?

A reliable source of lithium-6 target material is needed to produce the TPBARs for TVA’s tritium-producing reactors.  

The U.S. has not had an operational lithium-6 production facility since 1963 when the last COLEX (column exchange) enrichment line was shutdown.  COLEX was one of three lithium enrichment technologies employed at the Y-12 Plant in Oak Ridge, TN between 1950 and 1963.  The others technologies were ELEX (electrical exchange) and OREX (organic exchange).  All of these processes used large quantities of mercury.  At the time lithium-6 enrichment operations ceased at Y-12, a stockpile of enriched lithium-6 and lithium-7 had been established along with a stockpile of unprocessed natural lithium feed material.

There has been a continuing decline in the national inventory of enriched lithium-6.  To extend the existing supply, NNSA has instituted a program to recover and recycle lithium components from nuclear weapons that are being retired from the stockpile.

In May 2017, Y-12 lithium activities were adversely affected by the poor physical condition (and partial roof collapse) of the WW II-vintage Building 9204-2 (Beta 2).  

Shortly thereafter, NNSA announced the approval of plans for a new Lithium Production Facility at Y-12 to replace Building 9204-2.  The NNSA’s Fiscal Year 2020 – Stockpile Stewardship and Management Plan set an operational date of 2030 for the new facility.

5.6  Where is the tritium recovered?

Tritium is extracted from the irradiated TPBARs, purified and loaded into reservoirs at the Savannah River Site (SRS).  These functions are performed by “Savannah River Tritium Enterprise” (SRTE), which is the collective term for the tritium facilities, people, expertise, and activities at the SRS.

The first load of irradiated TPBARs were consolidated at Watts Bar and delivered to SRS in August 2005 for storage pending completion of the new Tritium Extraction Facility (TEF).  The TEF became fully operational and started extracting tritium from TPBARs in January 2007.  The tritium extracted at TEF is transferred to the H Area New Manufacturing (HANM) Facility for purification. In February 2007, the first newly-produced tritium was delivered to the SRS Tritium Loading Facility for loading into reservoirs for nuclear weapons.

From 2007 until 2017, the TEF conducted only a single extraction each year because of the limited quantities of TPBARs being irradiated in the TVA reactors. During this period, the TEF sat idle for nine months each year between extraction cycles.

In 2017, for the first time, the TEF performed three extractions in a single year using the original vacuum furnace. Each extraction typically involved 300 TPBARs.

In November 2019, SRTE’s capacity for processing TPBARs and recovering tritium was increased by the addition of a second vacuum furnace.

6.  Conclusions

In their “Fiscal Year 2020 – Stockpile Stewardship and Management Plan,”  the NNSA’s top-level goal is to “recapitalize existing infrastructure to implement a plan to produce no less than 80 ppy (plutonium pits per year) by 2030.”  This goal will drive tritium production demand, which in turn will drive demands for unobligated LEU to fuel TVA’s tritium-producing reactors and enriched lithium-6 for TPBARs.

The U.S. nuclear fuel cycle for the production of tritium currently is incomplete.  It is able to produce tritium by using temporary measures that are not sustainable:

  • Downblending HEU to produce LEU
  • Recycling tritium as the primary means for meeting current demand
  • Recycling lithium components

The next 15 years will be quite a challenge for the NNSA, DOE and TVA as they work to reestablish a complete, modern nuclear fuel cycle for tritium production.  There are several milestones on the critical path that would adversely impact tritium production if they are not met on schedule:

  • Higher tritium production goals for the TVA reactors: deliver  2,800 grams of tritium per two 18-month reactor cycles of production in TVA reactors by 2027
  • New Lithium Facility at Y-12 operational by 2030
  • New uranium enrichment facility operational, perhaps by the mid-2030s

There is a general lack of redundancy in the existing and planned future nuclear fuel cycle for tritium production.  This makes tritium production vulnerable to a major outage at a single non-redundant facility. 

You can download a pdf copy of this post here: https://lynceans.org/wp-content/uploads/2020/05/US-tritium-production-for-the-nuclear-weapons-stockpile-–-not-like-the-old-days.pdf

7.  Sources for additional information:

For general information:

For more information on Cold War-era Hanford tritium production:

For more information on Cold War-era SRP / SRS:

For more information on Cold War-era lithium enrichment at Oak Ridge Y-12:

For more information on the front-end of the US nuclear fuel cycle (uranium mining, milling, conversion & enrichment):

Exascale Computing is at the Doorstep

Updated 7 April 2020

Peter Lobner

The best current supercomputers are “petascale” machines.  This term refers to supercomputers capable of performing at least 1.0 petaflops [PFLOPS; 1015  floating-point operations per second (FLOPS)], and also refers to data storage systems capable of storing at least 1.0 petabyte (PB; 1015  bytes) of data.

In my 13 November 2018 post, I reported the latest TOP500 ranking of the world’s fastest supercomputers.  The new leaders were two US supercomputers: Summit and Sierra. A year later, in November 2019, they remained at the top of the TOP500 ranking.

  • Summit:  The #1 ranked IBM Summit is installed at the Department of Energy’s (DOE) Oak Ridge National Laboratory (ORNL) in Tennessee.  It has a LINPACK Benchmark Rmax (maximal achieved performance) rating of 148.6 PFLOPS (1.486 x 1017  FLOPS) and an Rpeak (theoretical peak performance) rating of 200.8 PFLOPS. Summit’s peak electric power demand is 10.01 MW (megawatts).
  • Sierra:The #2 ranked IBM Sierra is installed at the DOE’s Lawrence Livermore National Laboratory (LLNL) in California. It has an Rmax rating of 94.64 PFLOPS (0.9464 x 1017  FLOPS) and an Rpeak rating of 125.7 PFLOPS. Sierra’s peak electric power demand is 7.44 MW.

The next update of the TOP500 ranking will be in June 2020.  Check out their website here to see if the rankings change:   http:// https://www.top500.org

New exascale machines are only a year or two away

The next big step up in supercomputing power will be the arrival of “exascale” machines, which refers to supercomputers capable of performing at least 1.0 exaflops (EFLOPS; 1018  FLOPS), and also refers to data storage systems capable of storing at least 1.0 exabyte (EB, 1018  bytes) of data.  As you might suspect, there is intense international completion to be the first nation to operate an exascale supercomputer.  The main players are the US, China and Japan.

In the US, DOE awarded contracts to build three new exascale supercomputers: 

  • Aurora, announced in March 2019
  • Frontier, announced in May 2019
  • El Capitan, announced in March 2020

In this post, we’ll take a look at these three new supercomputers, each of which will be about ten times faster than the existing TOP500 leaders, Summit and Sierra.

Aurora supercomputer for ANL

The Aurora supercomputer is being built at Argonne National Laboratory (ANL) by the team of Intel (prime contractor) and Cray (subcontractor), under a contract valued at more than $500 million. 

Aurora supercomputer concept drawing.
Source: DOE / Argonne National Laboratory

The computer architecture is based on the Cray “Shasta” system and Intel’s Xeon Scalable processor, Xe compute architecture, Optane Datacenter Persistent Memory, and One API software. Those Cray and Intel technologies will be integrated into more than 200 Shasta cabinets, all connected by Cray’s Slingshot interconnect and associated software stack. 

Aurora is expected to come online by the end of 2021 and likely will be the first exascale supercomputer in the US.  It is being designed for sustained performance of one exaflops.  An Argonne spokesman stated, “This platform is designed to tackle the largest AI (artificial intelligence) training and inference problems that we know about.”

For more information on the Aurora supercomputer, see the 18 March 2019 ANL press release here:  https://www.anl.gov/article/us-department-of-energy-and-intel-to-deliver-first-exascale-supercomputer

Frontier supercomputer for ORNL

The Frontier supercomputer is being built by at ORNL by the team of Cray (prime contractor) and Advanced Micro Devices, Inc. (AMD, subcontractor), under a contract valued at about $600 million. 

Frontier supercomputer concept drawing.
Source:  DOE / Oak Ridge National Laboratory

The computer architecture is based on the Cray “Shasta” system and will consist of more than 100 Cray Shasta cabinets with high density “compute blades” that support a 4:1 GPU to CPU ratio using AMD EPYC processors (CPUs) and Radeon Instinct GPU accelerators purpose-built for the needs of exascale computing. Cray and AMD are co-designing and developing enhanced GPU programming tools.  

Frontier is expected to come online in 2022 after Aurora, but is expected to be more powerful, with a rating of 1.5 exaflops. Frontier will find applications in deep learning, machine learning and data analytics for applications ranging from manufacturing to human health.

For more information on the Frontier supercomputer, see the 7 May 2019 ORNL press release here:  https://www.ornl.gov/news/us-department-energy-and-cray-deliver-record-setting-frontier-supercomputer-ornl

El Capitan supercomputer for NNSA Labs

The El Capitan supercomputer, announced in March 2020, will be built at LLNL by the team of Hewlett Packard Enterprise (HPE) and AMD under a $600 million contract.  El Capitan is funded by the DOE’s National Nuclear Security Administration (NNSA) under their Advanced Simulation and Computing (ASC) program.  The primary users will be the three NNSA laboratories:  LLNL, Sandia National Laboratories and Los Alamos National Laboratory.  El Capitan will be used to perform complex predictive modeling and simulation to support NNSA’s nuclear weapons life extension programs (LEPs), which address aging weapons management, stockpile modernization and other matters.  

El Capitan supercomputer concept drawing.
Source:  Hewlett Packard Enterprise

El Capitan’s peak performance is expected to exceed 2 exaflops, making it about twice as fast as Aurora and about 30% faster than Frontier.

LLNL describes the El Capitan hardware as follows:  “El Capitan will be powered by next-generation AMD EPYC processors, code-named ‘Genoa’ and featuring the ‘Zen 4’ processor core, next-generation AMD Radeon Instinct GPUs based on a new compute-optimized architecture for workloads including HPC and AI, and the AMD Radeon Open Compute platform (ROCm) heterogeneous computing software.”  

NNSA’s El Capitan is expected to come online in 2023 at LLNL, about a year after ANL’s Aurora and ORNL’s Frontier.For more information on the El Capitan supercomputer, see the 5 March 2020 LLNL press release here:  https://www.llnl.gov/news/llnl-and-hpe-partner-amd-el-capitan-projected-worlds-fastest-supercomputer

Hewlett Packard Enterprise acquires Cray in May 2019

On 17 May 2019, Hewlett Packard Enterprise (HPE) announced that it has acquired Cray, Inc. for about $1.3 billion.  The following charts from the November 2018 TOP500 report gives some interesting insight into HPE’s rationale for acquiring Cray.  In the Vendor’s System Share chart, both HPE and Cray have a 9 – 9.6% share of the market based on the number of installed TOP500 systems.  In the Vendor’s Performance Share chart, the aggregate installed performance of Cray systems far exceeds the aggregate performance of a similar number of lower-end HPE systems (25.5% vs. 7.3%).  The Cray product line fits above the existing HPE product line, and the acquisition of Cray should enable HPE to compete directly with IBM in the supercomputer market.  HPE reported that it sees a growing market for exascale computing. The primary US customers are government laboratories.

The March 2020 award of NNSA’s El Capitan supercomputer to the HPE and AMD team seems to indicate that HPE made a good decision in their 2019 acquisition of Cray.

TOP500 ranking of supercomputer vendors, Nov 2018
Source:  https://www.top500.org
 

Meanwhile in China:

On 19 May 2019, the South China Morning Post reported that China is making a multi-billion dollar investment to re-take the lead in supercomputer power.  In the near-term (possibly in 2019), the newest Shuguang supercomputers are expected to operate about 50% faster than the US Summit supercomputer. This should put the new Chinese super computers in the Rmax = 210 – 250 PFLOPS range. 

In addition, China is expected to have its own exascale supercomputer operating in 2020, a year ahead of the first US exascale machine, with most, if not all, of the hardware and software being developed in China.  This computer will be installed at the Center of the Chinese Academy of Sciences (CAS) in Beijing.

You’ll find a description of China’s three exascale prototypes installed in 2018 and a synopsis of what is known about the first exascale machine on the TOP500 website at the following link: https://www.top500.org/news/china-spills-details-on-exascale-prototypes/

Where to next?

Why, zettascale, of course.  These will be supercomputers performing at least 1.0 zettaflops (ZFLOPS; 1021  FLOPS), while consuming about 100 megawatts (MW) of electrical power.

Check out the December 2018 article by Tiffany Trader, “Zettascale by 2035? China thinks so,” at the following link: https://www.hpcwire.com/2018/12/06/zettascale-by-2035/

JASON and NRAC Contracts Were Cancelled by the Pentagon in Early 2019 – JASON Has Survived but NRAC Has Not

Peter Lobner, updated 28 Jun 2019, 14 Dec 2019 & 12 May 2020

JASON and the Naval Research Advisory Committee (NRAC) are both established, independent advisory groups that have long histories of providing important scientific and technical advice to the U.S. government, primarily to Department of Defense (DoD) clients.  The Pentagon cancelled the JASON and NRAC contracts in early 2019.   Immediately, efforts were undertaken on several fronts to attempt to restore funding.   The efforts on behalf of JASON were successful, but NRAC was not so fortunate.

Following is an overview of these two advisory groups and an update on their current status.

1.  JASON

JASON is an independent advisory panel of elite scientists that was created in 1960 to address a wide range of scientific and technical issues, primarily for the U.S. military. Originally, the JASON panel had about 20 members, known informally as Jasons, increasing to about 40 members by the 1970s.  JASON maintains its independence by requiring that new members be selected by its existing members rather than by external sponsors.  

JASON is a very controversial organization with a very low public profile.  For a good introduction to JASON, I recommend Ann Finkbeiner’s 2006 book, “The Jasons: The Secret History of Science’s Postwar Elite,”  which is available from Amazon and other booksellers. You can watch an hour-long video created by Microsoft Research with Ann Finkbeiner providing an excellent narrative overview (no Powerpoint slides) on JASON here:

https://www.youtube.com/watch?v=FV1TBiwdZeg

Ann Finkbeiner notes: “Working in secrecy to solve highly classified problems for the Department of Defense, CIA, and NSA is an elite group of scientific advisors who provide the government with analyses on defense and arms control and they call themselves JASON.  Named for the hero in Jason and the Argonauts, the group grew out of the Manhattan Project and counts as its members scientists such as Freeman Dyson and Murray Gell-Mann.  Of the roughly one hundred Jasons over time, 43 have been elected to the National Academy of Sciences, eight have won MacArthur awards, one a Field’s Medal, and 11 have won Nobel Prizes.  Its members have gathered every summer since 1960, working in absolute secrecy and with unparalleled freedom.  The Jasons’ work poses vital questions: what role should the government play in scientific research? At what point is the inventor accountable for the hazards of the invention?”

You’ll find a list of JASON research topics compiled on Wikipedia here:

https://ipfs.io/ipfs/QmXoypizjW3WknFiJnKLwHCnL72vedxjQkDDP1mXWo6uco/wiki/JASON_(advisory_group).html

Most of the resulting JASON reports are classified.  You’ll find a list of unclassified JASON reports (and links) on the Federation of American Scientists (FAS) website at the following link: https://fas.org/irp/agency/dod/jason/

Since the late 1970s, the JASONs have been assigned tasks and been funded via Indefinite Delivery / Indefinite Quantity (IDIQ) contracts managed by MITRE Corporation.  The Office of the Secretary of Defense (OSD) issued MITRE’s most recent five-year IDIQ contract for managing JASON tasking and funding.   Task Orders are issued under the main IDIQ contract and the actual work is performed according to the individual task orders. The IDIQ contract structure broadly allows government agencies to commission a JASON study and fund it via a new task order.  MITRE’s IDIQ contract expired on 31 March 2019.  A follow-on IDIQ contract was in the works, but OSD cancelled that solicitation on short notice on 28 March 2019. 

On 10 April 2019, the article, “Pentagon Cancels Contract for JASON Advisory Panel,” written by Steven Aftergood, was posted on the FAS website at the following link: https://fas.org/blogs/secrecy/2019/04/pentagon-jason/

Aftergood speculated that, “The Pentagon move to cancel the JASON contract appears to be part of a larger trend by federal agencies to limit independent scientific and technical advice.”  

Additional resources related to JASON

See the following documents for more background information on JASON.

  • Joel Shurkin, “True Genius: The Life and Work of Richard Garwin, the Most Influential Scientist You’ve Never Heard of,” Prometheus Books, ISBN-13: 978-1633882232, 21 February 2017      

Lyncean link

At meeting #65 of the Lyncean Group in August 2011, the subject of our presentation was “Experience with the JASONs.”  See more at the following link:  https://lynceans.org/talk-65-82411/

2.  The Naval Research Advisory Committee (NRAC)

NRAC was established by Congressional legislation in 1946 and provided science and technology advice to the Navy for the past 73 years.  NRAC is the Navy counterpart to the Army Science Board and the Air Force Scientific Advisory Board.  Background information on NRAC is available on the Office of naval Research (ONR) website at the following link: https://www.onr.navy.mil/About-ONR/History/nrac

On 5 April 2019, Steve Aftergood reported that, “This week the U.S. Navy abruptly terminated its own scientific advisory group, depriving the service of a source of internal critique and evaluation.  Now it’s gone.  The decision to disestablish the Committee was announced in a March 29 Federal Register notice.”    The cancellation of the NRAC contract may be part of the apparent trend by federal agencies to limit independent scientific and technical advice.  You can read this report on the FAS website here: https://fas.org/blogs/secrecy/2019/04/nrac-terminated/

The former NRAC website appears to be offline: https://www.nrac.navy.mil

NRAC published reports from 1988 are still available online, now via the ONR website here: https://www.onr.navy.mil/en/About-ONR/History/nrac/reports-and-executive-summaries/reports-chronological

3. Update 28 June 2019:  NNSA issues new contract for JASON

In April 2019, the Department of Energy’s National Nuclear Security Administration (NNSA) issued a notice of intent (NOI) for a sole-source contract to provide funding for JASON through at least January 2020. You’ll find this NOI here: https://fas.org/irp/agency/dod/jason/nnsa-jason-noi.pdf

On 28 June 2019, Ann Finkbeiner posted an article entitled, “Jason—a secretive group of Cold War science advisers—is fighting to survive in the 21st century,” on the Science website at the following link: https://www.sciencemag.org/news/2019/06/jason-secretive-group-cold-war-science-advisers-fighting-survive-21st-century

This article provides a good overview of the history of JASON and offers the following view on future funding for the group.

“What happens when Jason’s contract with NNSA expires in 2020 is unclear. One possibility is yet another home within DOD: This month, the U.S. House of Representatives added a line to DOD’s preliminary budget directing the Office of the Under Secretary of Defense for Acquisition and Sustainment to pick up Jason’s contract.”

4.  Update 14 December 2019:  DoD contract for JASON is in the 2020 DoD Budget

On 11 December 2019, Steve Aftergood reported that Congress, via the National Defense Authorization Act for 2020, has directed the Department of Defense to reach an “arrangement with the JASON scientific advisory group to conduct national security studies and analyses.”  Aftergood identified the following specific JASON studies:

  • Performed in 2019:  Nuclear weapon pit aging (NNSA), bio threats (DOE), and fundamental research security (NSF)
  • Planned for 2020:  Assessments of electronic warfare programs, and options for replacing the W78 warhead currently carried by the Minuteman III intercontinental ballistic missile force

You can read this brief report on the FAS website at the following link: https://fas.org/blogs/secrecy/2019/12/dod-jason

You also can read the JASON’s 23 November 2019 letter report to NNSA on plutonium pit aging here: https://www.lasg.org/MPF2/documents/JASONs-pit-aging_23Nov2019.pdf

5.  Update 12 May 2020:  JASON COVID-19 pro bono study

On 11 May 2020, Jeffrey Mervis, writing for the Science.mag website, reported that JASON was engaged in a pro bono study, led by Massachusetts Institute of Technology (MIT) physicist Peter Fisher, of how to reopen university laboratories safely in the midst of the corona virus pandemic.  The results of this JASON study are expected in June 2020 and should be a useful resource for university officials and government agencies that are now drafting their own policies on reopening.

You can read the complete article here:  https://www.sciencemag.org/news/2020/05/secretive-jasons-have-advised-united-states-nuclear-war-next-how-reopen-labs-pandemic

Find more articles in Pete’s Lynx on the Lyncean Group website here: https://lynceans.org/petes-lynx/

Two US Supercomputers are Ranked Fastest in the World

Peter Lobner

In previous posts on 24 May 2015 and 28 June 2016, I reported on the TOP500 rankings of the world’s supercomputers.

In June 2013, China’s Tianhe-2 supercomputer at the National Supercomputer Center in Guangzho topped this this worldwide ranking with an Rmax Linpack score of 33 petaflops (1 petaflops = 1015  floating-point operations per second) and retained the first place position for two years. In June 2016, the new leader was another Chinese supercomputer, the Sunway TaihuLight at the National Supercomputer Center in Wuxi. TaihuLight delivered an Rmax Linpack score of 93 petaflops and remained at the top of the worldwide ranking for two years, until it was eclipsed in June 2018 by the US Summit supercomputer, then with an Rmax rating of 122.3 petaflops.

In the latest TOP500 ranking, the new leaders are two US supercomputers:  Summit (#1) and Sierra (#2).

Summit supercomputer.  Source: NVIDIA

The IBM Summit improved its past Linpack score to achieve an Rmax of 143.5 petaflops in the current ranking.  Summit is located at the Department of Energy (DOE) Oak Ridge National Laboratory (ORNL) in Tennessee.

  • 2,397,824 cores
  • 873 megawatts peak power

Sierra supercomputer. Source:  Lawrence Livermore National Laboratory / Randy Wong

The IBM Sierra also improved its past Linpack score to achieve an Rmax of 94.64 petaflops / second and move into second place, marginally ahead of China’s TaihuLight.  Sierra is located at the DOE Lawrence Livermore National Laboratory (LLNL) in California.

  • 1,572,480 cores
  • 438 megawatts peak power

The Summit and Sierra supercomputer cores are IBM POWER9 central processing units (CPUs) and NVIDIA V100 graphic processing units (GPUs).   NVIDIA claims that its GPUs are delivering 95% of Summit’s performance. Both supercomputers use a Linux operating system.

China’s Sunway TaihuLight was ranked 3rd, and Tianhe-2A was ranked 4th.  A total of five DOE supercomputers were in the top 10 positions.

You’ll find the complete 52ndedition (November 2018) TOP500 ranking here:

https://www.top500.org/lists/2018/11/

20 February 2019 Update:  Los Alamos National Laboratory (LANL) plans new supercomputer

The TOP500 ranking places LANL’s Trinity supercomputer (a Cray XC40) as the #6 fastest supercomputer in the world, but its performance (Rmax of 20.16 petaflops) is far below that of the #1 Summit supercomputer at Oak Ridge national Laboratory and the #2 Sierra supercomputer at Lawrence Livermore National Laboratory.

Source:  LANL

Not to be outdone, LANL issued a request for proposal (RFP) in February 2019 for a new supercomputer, to be named Crossroads, to support the lab’s missions for the National Nuclear Security Administration (NNSA).  A LANL spokesperson reported that, “High performance computing across the NNSA complex is used to assure the safety, security and effectiveness of the U.S. nuclear deterrent; to analyze and predict the performance, safety, and reliability of nuclear weapons and certify their functionality.”  Responses to the RFP are due by 18 March 2019.  Crossroads is expected to go online in 2021.